March 25, 2019 - August 30, 2019
2019-03-25T07:00:00
Moving Road Closures on North St from 3rd - 7th St 3/25 - 8/30 for Road Construction
Monday, March 25, 2019
Rieth-Riley will will be having moving road closures on North Street between 3rd Street and 7th Street for road construction from 3/25/19 to 8/30/19. Starting on 3/25/19 North Street will be closed between 3rd Street and 4th Street. Traffic will need to follow detour routes in each closure area. Utilities will start relocating starting the week of 3/25 and road construction will begin 4/1. Road construction will progress Eastbound closing off blocks of North Street as the work is accomplished (moving closures). 4th Street will be closed on or around 4/15 and will reopen the first week of May. As the work progresses finished blocks West of the closure area will open up to traffic. Follow the detour route signage that will be placed during the closures. Contact: Mike Rominger 765-656-4612