October 4, 2018, 7:00 AM - April 20, 2020, 5:00 PM
Sidewalk Closed East side 5th between Columbia & South & North side of South from 5th to alley2018-10-04T07:00:00Star City Crossing will have the sidewalk closed on the East side of 5th Street between South Street and Columbia Street, sidewalk will also be closed on the North side of South Street between 5th Street and the Alley just West of City Hall for the construction of a new building. This will be from 10/4/18 to 4/30/20. Chain link fence has been placed around site. Contact: Jon Caron 765-414-3995
Event LocationLafayetteIN47901 Star City Crossing will have the sidewalk closed on the East side of 5th Street between South Street and Columbia Street, sidewalk will also be closed on the North side of South Street between 5th Street and the Alley just West of City Hall for the construction of a new building. This will be from 10/4/18 to 4/30/20. Chain link fence has been placed around site. Contact: Jon Caron 765-414-3995
More Details
-
April 4, 2019, 7:00 AM - December 30, 2019, 5:00 PM
Walking trail closure & construction of new drives @ CR 430 S & S. 18th St 4/4 to 12/302019-04-04T07:00:00Kettlehut Construction will be installing temporary construction drives and eventually the installation of permanent new drives for TCPL South Branch Library. Closure locations approx. 50' of walking trail North of CR 430 S to the West of roundabout at intersection with S. 18th Street. Approx. 66' of walking trail on the West side of S. 18th Street to the North of roundabout at intersection with CR 430 S. from 4/4/19 to 12/30/19. Closures will be at construction drives for new South Branch Library. Existing walking trail will be removed and stone construction drive utilized until permanent drive paving and new concrete sidewalk can be installed late summer or early fall. Construction fencing and signage will be posted to alert general public of walking trail closures. Contact: Nate Secrest 765-447-2181
Event LocationLafayetteIN47901 Kettlehut Construction will be installing temporary construction drives and eventually the installation of permanent new drives for TCPL South Branch Library. Closure locations approx. 50' of walking trail North of CR 430 S to the West of roundabout at intersection with S. 18th Street. Approx. 66' of walking trail on the West side of S. 18th Street to the North of roundabout at intersection with CR 430 S. from 4/4/19 to 12/30/19. Closures will be at construction drives for new South Branch Library. Existing walking trail will be removed and stone construction drive utilized until permanent drive paving and new concrete sidewalk can be installed late summer or early fall. Construction fencing and signage will be posted to alert general public of walking trail closures. Contact: Nate Secrest 765-447-2181
More Details
-
June 10, 2019, 7:00 AM - October 25, 2019, 5:00 PM
Moving Road Closure-Vinton St., Longlois Dr. & 29th St. 6/10-10/25 WaterMain Replacement 2019-06-10T07:00:00TSW Utilities will be having moving road closures in the Vinton Subdivision. The following roads will have limited access, local traffic only: Vinton Street from Elmwood Ave. to Longlois Dr., Longlois Drive (South end) from Elmwood Ave. to Elmwood Ave., 29th Street from Longlois Dr. to Vinton St., Prairie Lane will have temporary road closure. Watch for Road Construction Ahead and Road Closed Ahead signs and Local Traffic Only signs. Contact: Terry Ratliff 317-354-5111
Event LocationLafayetteIN47901 TSW Utilities will be having moving road closures in the Vinton Subdivision. The following roads will have limited access, local traffic only: Vinton Street from Elmwood Ave. to Longlois Dr., Longlois Drive (South end) from Elmwood Ave. to Elmwood Ave., 29th Street from Longlois Dr. to Vinton St., Prairie Lane will have temporary road closure. Watch for Road Construction Ahead and Road Closed Ahead signs and Local Traffic Only signs. Contact: Terry Ratliff 317-354-5111
More Details
-
June 13, 2019, 3:00 PM - December 31, 2019, 5:00 PM
Sidewalk & South St Closed Indefinitely between Main St & 18th Street2019-06-13T15:00:00Sidewalk and South Street between Main Street and 18th Street has been closed Indefinitely. Contact: Mark Gick 765-807-1050
Event LocationLafayetteIN47901 Sidewalk and South Street between Main Street and 18th Street has been closed Indefinitely. Contact: Mark Gick 765-807-1050
More Details
-
July 23, 2019, 7:00 AM - December 31, 2019, 5:00 PM
Road Closure on Hartford Street from 14th to 15th St 7/23 to 12/31 for Demo2019-07-23T07:00:00Denney Excavating will have Hartford Street closed between 14th Street and 15th Street for the demolition of St. Francis Lafayette Hospital West and North wings and the St. Elizabeth Nursing School. Watch for road closed and detour signage. Contact: Suzanne Borges 317-554-2812
Event LocationLafayetteIN47901 Denney Excavating will have Hartford Street closed between 14th Street and 15th Street for the demolition of St. Francis Lafayette Hospital West and North wings and the St. Elizabeth Nursing School. Watch for road closed and detour signage. Contact: Suzanne Borges 317-554-2812
More Details
-
July 24, 2019, 7:00 AM - September 30, 2019, 5:00 PM
Lane Restrictions on South St from Main St to 18th St 7/24 to 9/302019-07-24T07:00:00Watch for Lane Restriction and Lane Shifts on South Street from Main Street to 18th Street. On South Street traveling West there will be no left turns. This is in preparation for demolition of building at the corner of Main Street and South Street.
Watch for signage and traffic control devices. Contact: Mark Gick 765-479-3517
Event LocationLafayetteIN47901 Watch for Lane Restriction and Lane Shifts on South Street from Main Street to 18th Street. On South Street traveling West there will be no left turns. This is in preparation for demolition of building at the corner of Main Street and South Street.
Watch for signage and traffic control devices. Contact: Mark Gick 765-479-3517
More Details
-
July 27, 2019, 7:00 AM - November 7, 2019, 5:00 PM
UPDATE: (Northbound 4th Street temporarily closed at Teal Road Intersection - Expect closure to last 2 weeks) Lane Closure Northbound lane of 4th St from 1850 S. 4th St to Club Ln intersection 7/27-11/72019-07-27T07:00:00UPDATE: Northbound lane of 4th Street will be temporarily closed from Teal Road to Club Lane. Please follow the traffic signs and detours to access businesses in this area. The northbound lane of 4th St. will re-open to 1850 S 4th Street once the work in this area is complete.
Atlas Excavating will have the Northbound lane of 4th Street from 1850 S. 4th Street to Club Lane Closed 7/27/19 to 11/7/19 for water main replacement work. Watch for detour, road closed signage. Watch for heavy equipment. Contact: Bret Dierdorf 765-637-9124
Event LocationLafayetteIN47901 UPDATE: Northbound lane of 4th Street will be temporarily closed from Teal Road to Club Lane. Please follow the traffic signs and detours to access businesses in this area. The northbound lane of 4th St. will re-open to 1850 S 4th Street once the work in this area is complete.
Atlas Excavating will have the Northbound lane of 4th Street from 1850 S. 4th Street to Club Lane Closed 7/27/19 to 11/7/19 for water main replacement work. Watch for detour, road closed signage. Watch for heavy equipment. Contact: Bret Dierdorf 765-637-9124
More Details
-
August 13, 2019, 8:00 AM - November 15, 2019, 5:00 PM
Road Restrictions on Underwood St. between 15th St & Erie St 8/13 - 11/152019-08-13T08:00:00Heartland Excavating will have Road Restrictions along Underwood Street between 15th Street and Erie Street working on concrete curb and gutter, drive approach and handicap ramp replacement. This will be 8/13/19 to 11/15/19. Watch for barrels and construction ahead signs. Contact: Mike Weathers 765-714-7686
Event LocationLafayetteIN47901 Heartland Excavating will have Road Restrictions along Underwood Street between 15th Street and Erie Street working on concrete curb and gutter, drive approach and handicap ramp replacement. This will be 8/13/19 to 11/15/19. Watch for barrels and construction ahead signs. Contact: Mike Weathers 765-714-7686
More Details
-
August 15, 2019, 7:00 AM - November 30, 2020, 5:00 PM
Sidewalk Closure 8/15/19 - 11/30/20 @ Loeb Stadium East side of Main St. & North side of Wallace2019-08-15T07:00:00J. R. Kelly Co. will have the following sidewalk closure at Loeb Stadium from 8/15/19 through 11/30/20. The sidewalks on the East side of Main Street and the North Side of Wallace Avenue will be closed adjacent to Loeb stadium through the end of the project in the fall of 2020. All pedestrian traffic will need to use the sidewalks on the other side of the street during this closure. Contact: Robert Mutzl 765-772-3991
Event LocationLafayetteIN47901 J. R. Kelly Co. will have the following sidewalk closure at Loeb Stadium from 8/15/19 through 11/30/20. The sidewalks on the East side of Main Street and the North Side of Wallace Avenue will be closed adjacent to Loeb stadium through the end of the project in the fall of 2020. All pedestrian traffic will need to use the sidewalks on the other side of the street during this closure. Contact: Robert Mutzl 765-772-3991
More Details
-
August 21, 2019, 7:00 AM - November 27, 2019, 5:00 PM
Lane Restrictions on Beck Ln. between between 9th St. & 18th St. 8/21-11/27 for curb & sidewalk replacement2019-08-21T07:00:00Rieth-Riley will have Lane Restrictions on Beck Lane between 9th Street and 18th Street 8/21/19 to 11/27/19 for curb, sidewalk, drive approach and handicap ramp removal and replacement. Lanes will be restricted at various times throughout the duration of the project. Expect daily lane restrictions. The intent is to do this in four phases. From Davis Drive to 9th Street on the North side. Davis Drive to 18th Street on the North side. 18th Street to Davis Drive on the South side. Davis Drive to 9th Street on the South side. There will be flaggers and signage daily. Contact: J. R. Beaman 765-404-4750
Event LocationLafayetteIN47901 Rieth-Riley will have Lane Restrictions on Beck Lane between 9th Street and 18th Street 8/21/19 to 11/27/19 for curb, sidewalk, drive approach and handicap ramp removal and replacement. Lanes will be restricted at various times throughout the duration of the project. Expect daily lane restrictions. The intent is to do this in four phases. From Davis Drive to 9th Street on the North side. Davis Drive to 18th Street on the North side. 18th Street to Davis Drive on the South side. Davis Drive to 9th Street on the South side. There will be flaggers and signage daily. Contact: J. R. Beaman 765-404-4750
More Details
-
August 26, 2019, 7:00 AM - November 29, 2019, 5:00 PM
Sidewalk Closure on East side of N. 26th St. between Ferry St. & South St. 8/26 - 11/292019-08-26T07:00:00Kettlehut Construction will have the sidewalk closed on the East side of N. 26th Street between Ferry Street and South Street for concrete demolition. Barricade sidewalk to direct pedestrian traffic to the West sidewalk along 26th Street. Contact: Nate Secrest 765-447-2181
Event LocationLafayetteIN47901 Kettlehut Construction will have the sidewalk closed on the East side of N. 26th Street between Ferry Street and South Street for concrete demolition. Barricade sidewalk to direct pedestrian traffic to the West sidewalk along 26th Street. Contact: Nate Secrest 765-447-2181
More Details
-
August 29, 2019, 7:00 AM - November 8, 2019, 5:00 PM
Gas Main installation along West side of S. 18th St from Logan Ave to Teal Rd 8/29 - 11/82019-08-29T07:00:00Vectren/CenterPoint Energy will be installing a gas main along the West side of S. 18th Street between Logan Avenue and Teal Road from 8/29/19 to 11/8/19. Flaggers, signage and cones will be out to divert traffic around construction activities avoiding closing down Southbound lane. Contact: Justin Lubke 765-543-5472
Event LocationLafayetteIN47901 Vectren/CenterPoint Energy will be installing a gas main along the West side of S. 18th Street between Logan Avenue and Teal Road from 8/29/19 to 11/8/19. Flaggers, signage and cones will be out to divert traffic around construction activities avoiding closing down Southbound lane. Contact: Justin Lubke 765-543-5472
More Details
-
September 3, 2019, 7:00 AM - October 11, 2019, 5:00 PM
Road Closure Alabama St from 2nd St to 4th St 9/3 - 10/11 for sewer project.2019-09-03T07:00:00Bowen Engineering will have Alabama Street closed in segments from 2nd Street to 4th Street 9/3/19 to 10/11/19 for the Sewer Separation and Pump Station Project. Detour signs will be set up accordingly along the routes. Through traffic will not be permitted in the affect areas. Please follow the alternate route which will be displayed by detour markers. Contact: Nick Isenhower 317-518-9721
Event LocationLafayetteIN47901 Bowen Engineering will have Alabama Street closed in segments from 2nd Street to 4th Street 9/3/19 to 10/11/19 for the Sewer Separation and Pump Station Project. Detour signs will be set up accordingly along the routes. Through traffic will not be permitted in the affect areas. Please follow the alternate route which will be displayed by detour markers. Contact: Nick Isenhower 317-518-9721
More Details
-
September 9, 2019, 7:00 AM - December 31, 2019, 5:00 PM
Sidewalk & Northbound lane Closure on 14th St. from Hartford St. to Tippecanoe St. 9/9 - 12/312019-09-09T07:00:00Denny Excavation will have a Sidewalk Closure and the Northbound lane closed in front of St. Elizabeth Hospital (for Demolition) on 14th Street between Hartford Street and Tippecanoe Street. This will be 9/9/19 to 12/31/19. Watch for traffic control devices. Contact: Suzanne Borges 317-554-2812
Event LocationLafayetteIN47901 Denny Excavation will have a Sidewalk Closure and the Northbound lane closed in front of St. Elizabeth Hospital (for Demolition) on 14th Street between Hartford Street and Tippecanoe Street. This will be 9/9/19 to 12/31/19. Watch for traffic control devices. Contact: Suzanne Borges 317-554-2812
More Details
-
September 9, 2019, 7:00 AM - November 1, 2019, 5:00 PM
Sidewalk Closed @ 3000 Main St for Bldg. Demo 9/9 to 11/12019-09-09T07:00:00Tri-Esco will have a sidewalk closure at 3000 Main Street for a building demolition 9/9/19 to 11/1/19. Watch for sidewalk closed signs and 6' tall chain link fence. Contact: John Wolff. 765-426-5503.
Event LocationLafayetteIN47901 Tri-Esco will have a sidewalk closure at 3000 Main Street for a building demolition 9/9/19 to 11/1/19. Watch for sidewalk closed signs and 6' tall chain link fence. Contact: John Wolff. 765-426-5503.
More Details
-
September 9, 2019, 7:00 AM - November 1, 2019, 5:00 PM
Temporary lane closures @ 2000 Main St 9/9 to 11/1 boring and pulling poles.2019-09-09T07:00:00Duke Energy will have periodic lane closures at 2000 Main Street 9/9/19 to 11/1/19 for boring and pulling power poles. Watch for traffic control. Contact: Owen Mason 765-446-4012
Event LocationLafayetteIN47901 Duke Energy will have periodic lane closures at 2000 Main Street 9/9/19 to 11/1/19 for boring and pulling power poles. Watch for traffic control. Contact: Owen Mason 765-446-4012
More Details
-
September 26, 2019, 1:00 PM - October 9, 2019, 5:00 PM
Road Closure on 4th St. @ Alabama St. continuation on sewer project 9/26-10/92019-09-26T13:00:004th Street Road Closure at Alabama Street. Bowen Engineering will be swapping intersection closures at 3rd Street and 4th Street on Alabama Street. At this time Southbound traffic on 3rd Street will open and a total closure at 4th Street will be implemented. When complete then all road access from 2nd Street to 4th Street will be paved and reopened. Watch for alternate routes which will be displayed by detour markers. Contact: Nick Isenhower 317-518-9721
Event LocationLafayetteIN47901 4th Street Road Closure at Alabama Street. Bowen Engineering will be swapping intersection closures at 3rd Street and 4th Street on Alabama Street. At this time Southbound traffic on 3rd Street will open and a total closure at 4th Street will be implemented. When complete then all road access from 2nd Street to 4th Street will be paved and reopened. Watch for alternate routes which will be displayed by detour markers. Contact: Nick Isenhower 317-518-9721
More Details